Contents
The free Mock CSCS Test for Supervisors below has 50 test questions and you have 45 minutes to answer. The CSCS Supervisor pass mark is 46/50. Click the Begin Test button to start.
CSCS Supervisor Card Mock Test
- Answered
- Flagged
You have 45 minutes to answer 50 multiple choice CSCS Mock Test questions for Managers and Professionals. You need to answer at least 46 out of 50 questions correctly to pass. Answers may be reviewed after each question or at the end of the test. Good luck!
Do you wish to proceed?
1349 votes - average 4.7 out of 5
Leave a comment
CSCS for Managers and Professionals
There are more than 1000 practice questions for Managers and Professionals in these mock tests. All tests last for 45 minutes and have 50 questions which have been randomly selected from 19 categories.
Managers Tests by Category
Supervisor Test Questions and Answers
Test Quick View
B HSE guidance
C Health and safety law
D The Health and Safety At Work etc. Act
Explanation: All other regulations, codes, and guidance complement or build upon the The Health and Safety At Work etc. Act.
B A project lasting 35 working days with no more than 12 workers at any one time
C A project lasting 35 working days, with 25 workers
D A project that is 450 person days
E A project that is 510 person days
Explanation: Projects are notifiable under two circumstances: when they exceed 30 working days in length and at any point involve more than 20 people working simultaneously; or, when the project takes longer than 500 person days.
B The client
C The contractor or principal contractor
D The designer or principal designer
Explanation: The contractor, or principal contractor, is responsible for putting together the construction phase plan.
B Arrangements outlining duties of each role in the responsibility tree
C Medical insurance appropriate to each worker's position
D Monthly assessments by a Health and Safety Executive inspector
E Organisational structure with responsibility tree
F Policy statement for health and safety
Explanation: Health and safety management policy requires that companies have a health and safety policy statement, along with an organisational structure and responsibility tree, with clear duties assigned to each position in the tree.
B Assign a numerical value to how likely and severe each risk might be
C Numerically rank the risks involved in the task
D Take specific measurements and reading to help assess the risk
Explanation: Semi-quantitative risk assessments also consider residual risks, and categorise them as either high, medium, or low.
B Ask if everyone has understood
C Issue a written test
D Issue them with a copy of all induction information
E Monitor the work of new inductees
Explanation: You should actively ensure inductees have understood the information. You might issue a written test, and if you are asking comprehension questions verbally you must ensure that you are specific and direct.
B Proactive
C Reactive
D Spontaneous
E Systematic
Explanation: Records are, broadly speaking, either proactive (e.g., machine inspection records), or reactive (e.g., accident investigation records).
B They must be destroyed once the project is completed
C Three months after the final entry
D Three years after the final entry
Explanation: Accident records must be archived for three years after the final date entered into the book.
B 14 units per week
C 16 units per week
D 18 units per week
Explanation: As of 2016, the NHS recommended alcohol intake be restricted to 14 units per week for both men and women.
B It does not
C One year
D Three years
Explanation: The certification period for first aiders is three years, following which first aiders will need to carry out a full course of training again. It is recommended that refresher courses be taken during these three years.
B Assess the situation FIRST
C Call for qualified help, and stay with the casualty
D Do NOT move the casualty unless it is in order to preserve life
E Go to fetch qualified help
F Move the casualty somewhere warm and dry in order to preserve life
Explanation: If you are the first on the scene of a serious casualty, your first action must always be to assess the situation. Do not move the casualty unless it is necessary to preserve life, send for qualified help, and stay with them.
B One first aider trained in Emergency First Aid at Work (EFAW)
C Three first aiders trained in First Aid at Work (FAW)
D Two appointed people
Explanation: For a site with 25-50 employees, you are recommended to have at least one first aider trained in EFAW.
B Use barrier cream on gloves
C Use barrier creams - but not on gloves
D Use hand conditioning cream
E Wash difficult stains with spirits or solvents
Explanation: Employees can take simple additional steps to protect their skin. These include using barrier creams (but not on gloves), and hand conditioning cream and cleaners. Spirits and solvents must not be used, as they strip oils from your skin leaving it less protected.
B When no other RPE is available
C When sanding wood
D When working in enclosed spaces
Explanation: Nuisance dust masks do not meet any current PPE or RPE standards, and should not be used as such.
B Look for CE marked products
C Search online for the best deal
D Seek out a reputable supplier
E Seek out a supplier that many people are purchasing from
F Test it yourself first
Explanation: The production of ineffective, cheap counterfeit PPE is on the rise. So ensure you are buying from a reputable supplier and that products are CE marked - do not be tempted by the cheapest option.
B GDPR regulations
C Safety data sheet
D Supplier's consultant
Explanation: The safety data sheet for hazardous substances must be referred to when you are putting together a COSHH assessment for activity involving them.
B That it is properly face-fitted
C That it is suitable for the worker's physical condition
D That the worker removes any facial hair
Explanation: RPE must be properly face-fitted, and suitable for both the task at hand and the worker's physical condition (e.g., if they have a breathing condition). If facial hair is not removed, a suitable alternative must be found.
B To ensure employers have comprehensive and effective safety policies on the use of chemical substances
C To ensure hazardous substances are not used on site
D To provide comprehensive training to apprentices on the nature of chemical substances
Explanation: The EU regulation REACH (Registration, Evaluation, Authorisation, and restriction of Chemical substances) ensures manufacturers provide good information regarding the safe use and associated hazards of chemical substances.
B It is inexpensive
C It is relatively fast
D It is the ONLY way to establish the presence of asbestos
E It is the most effective method, but other reliable alternatives are available
F It takes longer than alternative methods
Explanation: Laboratory analysis is the only way to establish the presence of asbestos - but it is relatively inexpensive and fast.
B You ARE doing work for a domestic client, and therefore they are NOT legally required to keep an asbestos register
C You are NOT doing work for a domestic client, and MUST be granted access to the asbestos register
D You are NOT doing work for a domestic client, but housing associations are NOT legally required to keep an asbestos register
Explanation: Housing associations are classified as non-domestic clients, and they must therefore both keep an asbestos register and give contractors access to it.
B 6 hours
C 8 hours
D The length of a standard on-site shift (variable)
Explanation: The daily dose value describes personal noise exposure over an 8 hour period.
B Daily dose: 90 dB(A)
C Peak level: 135 dB(C)
D Peak level: 150 dB(C)
Explanation: The lower exposure action level is 80 dB(A) for daily dose, and 135 dB(C) for peak level.
B The employees
C The employer
D The health and safety inspector
E The provider of manual handling aids
Explanation: Employers and employees are both legally responsible for safely planning and carrying out manual handling.
B Only at the client's request
C Only if there is a risk to public safety
D Only when construction is about to commence
Explanation: Sites must be secured using hoarding and lockable gates immediately upon possession of the site.
B Mandatory signs are yellow
C Prohibition signs are blue
D Prohibition signs are red
E Warning signs are red
F Warning signs are yellow
Explanation: Mandatory signs are blue, prohibition signs are red, and warning signs are yellow
B All employees
C The client
D The principal contractor
Explanation: By law, a responsible person must be appointed by the Principal Contractor to be in charge of the fire risk assessment.
B A marshal manages the site, a warden manages an area within it
C A warden is trained in EFAW, a marshal is not
D A warden manages the site, a marshal manages an area within it
Explanation: A fire marshal manages fire safety for the site; a fire warden is responsible for a specified area within it.
B A disconnected circuit is a dead circuit
C An isolated wire is a dead wire
D Material is not a conductor unless it is used in a circuit
Explanation: Isolation and disconnection do not equate to something being dead, and an item may become charged by induction or static charging, not by being live. Conductors do not have to be part of circuits.
B Ensure the correct PPE is being worn
C Ensure wires are properly insulated
D Use a portable RCD
Explanation: Residual Current Devices (RCDs) must be used when the use of mains-powered hand tools cannot be avoided.
B Checking and supervising
C Issuing permits for loading/unloading
D Leading the temporary works co-ordinator
E Planning the temporary works construction
F Taking legal responsibility for any accidents happening during temporary works
Explanation: Temporary works supervisors have a number of duties, which are likely to include issuing permits for loading/unloading, assisting the temporary works co-ordinator, and the usual checking and supervision.
B Leak detector
C RCDs
D Whip checks
Explanation: Whip checks must be fitted on hose joints to prevent injury if the joint breaks.
B When plant is in use
C When space permits
D When there are more than 5 vehicles in operation on site
Explanation: Pedestrian routes should be put in place where space permits.
B Install a warning sign, flag, or beacon
C Nothing in particular if the load is secured
D This must NEVER happen
Explanation: Projecting loads must be indicated - you might use a flag, a sign, or a beacon to do so.
B So spillages can be detected and contained
C So spillages do not create a fire hazard
D So spillages do not create hazardous vapour
Explanation: Impervious surfaces are water-resistant. Any spillages or leaks will therefore be clearly visible, and also easier to contain.
B If the load being lifted contained hazardous materials
C If there is an injury
D Under all circumstances
Explanation: All failure, collapse, or overturning of lifting equipment must be reported to the HSE, under all circumstances. It constitutes a notifiable dangerous occurrence.
B Atmospheric pressure
C Flight scheduling
D Planning restrictions
Explanation: There may be airspace restrictions in place near airports - if a tower crane of being used, these must be checked.
B They must be accompanied by the use of hand-held signs
C They must be restricted to those specified in the Health and Safety Regulations
D They must only be given by people over the age of 18
E They must only be used where alternative navigation tools like CCTV and mirrors cannot be provided
Explanation: Hand signals must conform to those specified in site regulations, and can only be given by trained persons.
B They must be regularly reset
C They only measure latitudinal instability
D They should NEVER be used
Explanation: LMI units must be regularly reset, and only help monitor longitudinal instability.
B This will affect the operator's sightline
C This will affect the weight of the load that can be lifted
D This will allow for more weight to be lifted
E This will require a permit to work
Explanation: Keeping the bucket in place on an excavator used for lifting will affect the operator's sightline, and also the weight of the load that can be lifted. This is because the weight of the bucket must be factored into the safe working load.
B From a fixed access scaffold
C From a ladder rested against the chimney stack
D From a mobile elevating work platform
Explanation: Fixed access scaffolds offer the safest way of accessing chimneys for work.
B For less than 30 minutes
C So the worker is side-on to their activity
D The ladder is set up at a 1:5 ratio
Explanation: Ladders must be used for light work of short duration only, and must be correctly angled and oriented.
B The safety manual issued by the provider must be consulted in order to carry out the activity safely
C This must never happen
D Warning signs must be put up
Explanation: The removal of guard rails can only be done with permission, and by a person who is trained and competent.
B 2.5m
C 2m
D There is no specified depth
Explanation: The specified depth has been removed from health and safety regulations - whether or not to install supports must now be decided based on a risk assessment.
B Ensure the excavation is adequately ventilated
C Ensure the excavation supports are designed to accommodate it
D Ensure vehicle traffic does not come near to the excavation
E Ensure water in the bottom of the excavation is properly pumped
Explanation: Surcharging is damage resulting from pressure applied to the sides of an excavation. Ensure traffic routes do not pass by the excavation - and that the excavation is adequately supported if this is not possible.
B Fog
C Heavy rain
D Wind
Explanation: When soil becomes waterlogged, or dries out, this affects the nature of the ground and therefore the stability of any excavation.
B Begin by compacting selected backfill around the service
C Begin by placing warning tiles or tape around the service
D Begin by tipping hardcore around the service
Explanation: Backfilling must be done carefully to ensure no damage is done to the service - as such, you should begin by compacting selected backfill around it.
B When the atmosphere becomes stale
C When the atmosphere becomes too hot
D When the atmosphere is filled with fumes
Explanation: Enriching oxygen in the atmosphere will make organic materials exceptionally combustible, and fires especially dangerous. This should not be practiced.
B Lifelines must be provided
C Resuscitation equipment must be provided
D Secondary communications must be provided
Explanation: Resuscitation equipment must be provided, and workers must be trained in using it.
B In a separate underground unit
C In the open air
D In the store
Explanation: Decanting must not be carried out in the store.
B The building is susceptible to gas leaks
C There will be high unintended heat loss
D There will be low unintended heat loss
Explanation: A low air tightness testing result means there is good insulation - and therefore low unintended heat loss.




















