1. What do The Work at Height Regulations require of crane operations?

According to the Work at Height Regulations, crane operations must ensure that work at height is avoided wherever reasonably practicable. If work cannot be done from the ground, a safe system of work must be implemented, including suitable equipment and trained operators. The regulations require risk assessments to be conducted, with consideration of rescue plans and emergency procedures. Safety measures such as guard rails, edge protection, and personal protective equipment must be utilized to prevent falls. Regular inspections and maintenance of the crane and its components are also required to ensure safe operation.

2. What is the difference between a contract lift and a 'standard' crane hire?

The key difference between a contract lift and standard crane hire lies in the level of responsibility assigned to each party. In a contract lift, the crane provider takes full responsibility for the lift, including organizing a qualified operator and supervising the lift. This option ensures compliance with regulations and provides additional peace of mind, but it tends to be more costly. 'Standard' crane hire, on the other hand, places responsibility on the hirer to plan and execute the lift, including providing a qualified operator. This option may offer more flexibility and cost savings, but also places greater liability on the hirer.

3. At the end of the shift: a)  in what position should jibs and trolleys be left in and b)  why?

At the end of the shift, the jibs and trolleys of a tower crane should ideally be left in the "weathervaning" position. This means that the jibs should be left perpendicular to the wind direction, while the trolleys should be positioned near the mast. This is important for two reasons. First, it helps reduce wind resistance and minimize the risk of the crane being affected by strong gusts. Second, it allows the crane operator to easily start the crane the next day without any major adjustments. Ensuring safe and efficient operation of the crane is paramount.

4. On a busy construction site, how would the slinger/signaller be identified to the crane operator?

On a busy construction site, the slinger/signaller would typically be identified to the crane operator through the use of hand signals or radio communication. Hand signals are often standardized and include gestures to indicate movements such as hoisting, lowering, slewing, and stopping. These signals allow the slinger/signaller to convey instructions clearly and safely to the crane operator. Additionally, hi-vis clothing, fluorescent vests or armbands may be worn by the slinger/signaller for easy visual identification. It is important to establish clear communication protocols and safety procedures between the slinger/signaller and the crane operator to ensure a smooth operation.

5. a)  What checks should be made to the ground conditions and b)  when should the checks be made?

a) The checks for ground conditions for a tower crane should include assessing the soil stability and load-bearing capacity of the site, ensuring it can support the crane's weight and movements. Ground surveys, geotechnical reports, and soil tests are essential to identify any potential issues.

b) The checks for ground conditions should be made before the tower crane is installed on-site. It's crucial to conduct these checks during the initial planning and preparation stages of the construction project to ensure the safety and stability of the crane and prevent any potential accidents or damage to the surrounding area.

6. What is jib deflection and when does it occur?

Register to view the answer to this question

Jib deflection refers to the bending or flexing of the horizontal arm, or jib, of a tower crane. It typically occurs when the crane is under load and subject to external forces, such as wind, or when the jib is extended to its maximum length. Jib deflection can impact the stability and performance of the crane, and if excessive, it may compromise safety. It is important to monitor and control jib deflection within acceptable limits to ensure the crane operates safely and effectively. Site conditions and specific crane design factors influence the amount of jib deflection experienced.

7. If a load of 20 tonnes is lifted on four falls or lines of rope, what is the tension in each fall or line?

Register to view the answer to this question

To determine the tension in each fall or line, we divide the load by the number of falls or lines. In this case, if a load of 20 tonnes is lifted on four falls, the tension in each fall would be 5 tonnes (20 tonnes divided by 4 falls). This assumes that the load is evenly distributed among the falls. Remember to consider safety factors and ensure that the crane's capacity is not exceeded.

8. State the functions or job role of the following personnel: a)  Appointed Person b)  Crane Supervisor c)  Slinger

Register to view the answer to this question

a) The appointed person is responsible for planning and managing lifting operations. They assess the site, calculate lifting capacities, and create method statements. They ensure that lifting activities are carried out safely and within regulations.

b) The crane supervisor oversees the operation of the crane. They are responsible for coordinating the lifting activities, ensuring that the crane is operated safely, and following any instructions from the appointed person or site management.

c) The slinger works closely with the crane operator. They attach and detach loads to and from the crane, directing the movement of the load during lifting operations and signaling the crane operator. They also ensure that slinging and lifting equipment is in good condition.

9. Using the Operator's Manual or other, state the maximum wind speed the crane may be operated in. Note: The Operator's Manual for the machine being used for the test MUST be available for reference by the candidate.

Register to view the answer to this question

The maximum wind speed in which a tower crane may be operated can vary depending on the specific make and model of the crane. It is important to refer to the Operator's Manual for the particular crane being used, as this document will provide the manufacturer's specifications and guidelines. Without access to the Operator's Manual for the specific crane, it is not possible to provide an accurate answer.

10. At the end of the shift: a)  how should cab cleanliness be maintained and b)  explain why?

Register to view the answer to this question

At the end of the shift, the cab of a tower crane should be cleaned to maintain good hygiene and safety. It is important to remove any dirt, debris, or spills to prevent slip hazards and to ensure that the crane operator has a clear and unobstructed view. Regular cleaning also helps maintain the condition of the cab, preventing issues such as rust or damage to equipment. Additionally, a clean cab promotes a professional and organized working environment. Cleaning the cab at the end of the shift ensures that it is ready for the next operator to use safely and efficiently.

11. a)  What is meant by the lifting capacity of the crane and b)  who determines it?

Register to view the answer to this question

a) The lifting capacity of a tower crane refers to the maximum weight it can safely lift and transport. It is an important specification to ensure the crane can handle the loads required for the construction project.

b) The lifting capacity of a tower crane is typically determined by the crane manufacturer. They test and evaluate the crane's structural integrity, stability, and operational limitations to establish its lifting capacity. It is crucial to adhere to the manufacturer's guidelines and not exceed the specified lifting capacity to maintain safety on the construction site.

12. What are the possible outcomes of facing prosecution for not complying with legislation and regulations?

Register to view the answer to this question

Facing prosecution for not complying with legislation and regulations in the construction industry could result in a number of outcomes. These can include financial penalties, such as fines, as well as potential imprisonment for individuals found personally liable. In addition, the company may suffer reputational damage, leading to loss of clients and business opportunities. Furthermore, there may be restrictions or bans imposed on the company's ability to tender for future projects. It is crucial to ensure compliance with legislation and regulations to avoid these potential consequences. Consulting with legal professionals and implementing robust compliance measures is advisable.

13. If fitted, what is the purpose of the flags situated on the jib?

Register to view the answer to this question

The flags on a tower crane's jib serve as visual aids to improve safety on a construction site. These flags are usually bright in color and are placed at specific locations on the jib, such as the outer end and the midsection. They help provide clear visibility to the crane operator and other workers, highlighting the position and movement of the jib. This is particularly important when operating in low-light conditions or when there are obstructions that could obstruct the view. The flags assist in preventing collisions and enhancing overall safety on the construction site.

14. Using the lifting capacity diagrams (Annex A, B and C): Annex A - using a 55-metre jib set-up: a)  what is the lifting capacity in tonnes at 34 metres radius and b)  what radius can a load weighing 5.80 tonnes be placed at?

15. Where should the Operator's Manual be kept and why?

Register to view the answer to this question

The Operator's Manual for a tower crane should be kept on-site, accessible to the crane operator. It is vital for the operator to have quick access to the manual for reference on safe operation, maintenance procedures, troubleshooting, and emergency protocols. Having the manual readily available helps ensure that the operator has the necessary information at hand to operate the crane safely and efficiently, reducing the risk of accidents and improving overall productivity.

16. If the words STOP NOW are given to the crane operator by radio during the lift, what action must the operator take?

Register to view the answer to this question

If the crane operator is instructed to "STOP NOW" by radio during the lift, they must immediately cease all crane operations and bring the crane to a safe and controlled stop. This could involve stopping the hoisting, slewing and any other crane movements. The reason behind this instruction should be ascertained and the necessary precautions and corrective measures should be implemented before any further crane operations are resumed. Safety is paramount, and swift compliance with such stop instructions is vital to ensure the well-being of both the operator and the surrounding personnel.

17. If assisting in erecting a tower crane, why is it important that the manufacturer's procedures are followed precisely?

Register to view the answer to this question

Following the manufacturer's procedures precisely is crucial when erecting a tower crane because they are designed and engineered to ensure safety and optimal performance. Manufacturers have extensive knowledge and expertise in the construction of their own cranes, and their procedures have been tested and refined to minimize risks and ensure proper functioning. Deviating from these procedures could compromise the structural integrity of the crane, increase the risk of accidents, and invalidate any warranties or insurance coverage. By adhering to the manufacturer's procedures, you ensure that the crane is assembled correctly, reducing the likelihood of costly errors or safety incidents.

18. During your time on site how can you create a good relationship and ensure that the client may want you back on site?

Register to view the answer to this question

To create a good relationship with the client on site, it is important to prioritize effective communication, collaboration, and professionalism. Be proactive in addressing any concerns or issues promptly. Seek to understand the client's needs and expectations for the project, and strive to meet those requirements. Deliver quality workmanship and adhere to agreed-upon timelines. Demonstrate a strong work ethic, reliability, and a positive attitude. Foster a sense of trust and transparency in all interactions with the client. Continuously seek feedback and make improvements accordingly. By consistently demonstrating professionalism and delivering results, the client is more likely to want you back on site.

19. When should maximum permissible wind speeds be reduced?

Register to view the answer to this question

Maximum permissible wind speeds for tower cranes are typically reduced when certain conditions are present, such as:

1. Site location: In areas where the wind is known to be strong or gusty due to geographical factors.
2. Building height: When the tower crane is being used for construction of tall buildings, as higher elevations are more susceptible to stronger winds.
3. Crane configuration: If the crane is operating with its boom fully extended or with a heavy load, wind speeds may need to be reduced to ensure stability.

Ultimately, the decision to reduce maximum wind speeds should be made in accordance with local regulations and industry best practices.

20. A crane has been erected on site. What must take place before any site lifting takes place?

Register to view the answer to this question

Before any site lifting takes place, several essential steps need to be taken. Firstly, a thorough risk assessment should be conducted to identify potential hazards and devise appropriate control measures. This should include assessing factors such as weight loads, lifting distances, and ground conditions. Secondly, all personnel involved in lifting operations must be properly trained and competent. This includes crane operators, riggers, and signalers. Finally, a lift plan should be developed, detailing the specific procedures, safe positions, and relevant communication methods to be followed during the lifting operation. Adhering to these steps helps ensure that site lifting is conducted safely and efficiently.

21. a)  At the end of the shift what THREE security measures should be applied and b)  why?

Register to view the answer to this question

a) At the end of the shift, three security measures that should be applied for a tower crane are:
1. Ensuring the crane is securely parked and immobilized to prevent unauthorized use or accidental movement.
2. Removing any valuable tools or equipment from the crane to prevent theft or damage.
3. Locking the crane operator's cabin and securing any access points to prevent unauthorized entry and safeguard against vandalism or tampering.
b) These security measures are essential to protect the tower crane from theft, unauthorized use, and vandalism, reducing the risk of accidents and ensuring the crane's safe and secure condition for the next shift.

22. If facing the crane whilst using the remote unit what can happen?

Register to view the answer to this question

When facing a tower crane and using the remote unit, there are potential hazards to consider. Firstly, it is crucial to be aware of your surroundings and any other workers in the vicinity who might be at risk. Additionally, if you accidentally press the wrong controls or operate the crane incorrectly, it could lead to unsafe movements, causing damage to the crane, the load being lifted, or even endangering people nearby. Therefore, it is essential to undergo proper training and follow the manufacturer's instructions carefully to prevent accidents and ensure safe crane operation.

23. When can you use the high speed hoist?

Register to view the answer to this question

The high-speed hoist on a tower crane is typically used for vertical movement of loads at a faster pace. It is suitable when time constraints are a priority, such as when there are tight project schedules or when there is a need to quickly move lightweight loads to different levels. However, it is important to ensure that the high-speed hoist is used within the manufacturer's recommended capacity and safety guidelines.

24. How can a qualification or card benefit a crane operator?

Register to view the answer to this question

Obtaining a qualification or card in tower crane operation can provide numerous benefits to a crane operator. Firstly, it demonstrates their competence and expertise in operating a tower crane, enhancing their professional reputation and increasing employment opportunities. It also ensures compliance with industry-specific regulations and health and safety standards, reducing the risk of accidents or incidents on-site. Additionally, having a qualification or card can lead to higher earning potential, as employers often give preference to qualified crane operators. Overall, it provides credibility, career progression, and increased job security in the construction industry.

25. What is the purpose of a risk assessment?

Register to view the answer to this question

The purpose of a risk assessment in the context of a construction site is to identify potential hazards and evaluate the level of risk associated with them. It helps ensure that suitable control measures are in place to mitigate those risks effectively. Specifically for tower cranes, a risk assessment would help identify potential hazards such as collision risks, overloading, inadequate ground conditions, and proximity to power lines. By conducting a risk assessment, employers and site managers can prioritize actions to minimize these risks and promote a safe working environment for all construction workers and members of the public.

26. Apart from lifting using the hook, what other type of work can Tower cranes undertake?

Register to view the answer to this question

Tower cranes are widely used in the construction industry for various tasks other than lifting. These cranes can perform operations such as loading and unloading materials, transferring heavy objects horizontally, and even assembling prefabricated components. They are essential for erecting steel structures, placing concrete panels, and assisting with the installation of curtain walls. The versatility of tower cranes also allows them to be used for precision tasks like placing delicate equipment or conducting maintenance work at height. Their long reach and flexibility make them indispensable machines on construction sites.

27. Describe the THREE main types of tower crane base options

Register to view the answer to this question

The three main types of tower crane base options are:
1. Static Base, which is the traditional fixed base option that requires a concrete foundation.
2. Ballasted Base, where the tower crane is secured by a central ballast block, usually made of concrete or a combination of concrete and steel weights.
3. Mobile Base, which allows the tower crane to be moved easily on site using wheels or tracks. Each base option has its own advantages and considerations, such as the required preparation time, ease of relocation, and weight-bearing capacity.

28. The lifting plan will specify a minimum distance that your jib must be kept away from overhead electricity lines/pylons. a)  Explain why your jib must be kept away and b)  what are the consequences of coming in to contact with the lines/pylons?

Register to view the answer to this question

a) The jib of the tower crane must be kept away from overhead electricity lines/pylons to prevent electrical accidents and ensure safety. Contact between the jib and the lines can lead to electrical shock or short-circuits, posing a significant risk to the crane operator and others working in the vicinity. Following the specified minimum distance helps maintain sufficient clearance and reduce the risk of electrical hazards.
b) The consequences of coming into contact with the lines/pylons can be severe. It may result in electric shock, equipment damage, fire, or even fatalities. Additionally, it could interrupt the power supply, leading to disruption and potential financial losses. Adhering to the regulations and maintaining the minimum distance is crucial to avoid these risks.

29. What prevents the hook block from contacting the jib pulley?

Register to view the answer to this question

To prevent the hook block from contacting the jib pulley on a tower crane, there are a few safety mechanisms in place. One of the primary mechanisms is the use of a preventer mechanism, which consists of a rubber buffer or bump stop. This prevents the hook block from reaching the jib pulley during the operation. Additionally, there are limit switches and sensors installed that detect the position of the hook block and provide feedback to the crane's control system. These safety measures ensure that the hook block and jib pulley do not come into contact during crane operations.

30. What is the purpose of counterweight(s) on the crane?

Register to view the answer to this question

The counterweights on a tower crane are necessary for stability and balance. They counteract the force exerted by the load being lifted and provide a stable base for the crane to operate safely. The mass of the counterweights allows the crane to maintain its equilibrium and prevents it from tipping over. The placement and amount of counterweight required depends on the crane's configuration and the maximum load it is designed to lift.

31. List SIX typical subject areas that should be covered in a site induction.

Register to view the answer to this question

The six typical subject areas that should be covered in a site induction for a tower crane are:
1. Safety procedures and regulations specific to tower crane operation,
2. Emergency procedures, including evacuation plans and first aid protocols,
3. Site-specific hazards and risk assessments, particularly those applicable to tower crane operations,
4. Communication protocols and reporting systems,
5. Equipment inspection and maintenance requirements for tower cranes, and
6. Roles and responsibilities of individuals involved in tower crane operations, including operators, banksmen, and supervisors.

32. If a load is lifted up and the hook block is not above the centre of the load what can happen?

Register to view the answer to this question

If the hook block is not positioned directly above the center of the load when lifted by a tower crane, it can result in an unbalanced load. This can cause the load to swing or tilt, leading to instability and potential accidents. It is crucial to ensure the hook block is correctly aligned with the center of the load to maintain balance and safety during lifting operations.

33. a)  What is the purpose of a Method Statement and b)  what is required of the operator?

Register to view the answer to this question

a) A Method Statement in construction outlines how a task will be carried out safely and efficiently. It includes the sequence of work, equipment to be used, safety measures, and potential hazards. Its purpose is to ensure that everyone involved understands the steps and risks involved, allowing them to work in a controlled manner.
b) The operator of a tower crane must be trained and competent. They should follow the instructions in the Method Statement, operate the crane within safe working limits, and monitor nearby personnel to prevent accidents. Regular inspections and maintenance of the crane are also the operator's responsibility.

34. If setting up to lift loads near a pedestrianised area, what main factor needs to be taken into account?

Register to view the answer to this question

The main factor to consider when setting up a tower crane near a pedestrianised area is safety. Ensure that the crane is placed in a secure position and its movement is restricted to avoid any potential hazards to pedestrians. Additionally, consider the crane's swing radius and ensure that it does not encroach onto pedestrian pathways. Adequate barriers, warning signs, and flaggers may be required to maintain a safe distance between the crane and pedestrians. Consult local regulations and engage with relevant authorities to ensure compliance and minimize risks to pedestrians.

35. a)  Where must the load radius diagram be located and b)  what information must it contain?

Register to view the answer to this question

a) The load radius diagram must be prominently displayed near the tower crane operator's cab for easy reference.
b) The load radius diagram must provide information about the maximum working radius of the crane at various load capacities. It should include clear markings at different load capacity points, indicating the corresponding working radius. This allows the crane operator to determine the safe working radius based on the load being lifted.

36. Why would hard hats (head protection) be needed when climbing a tower crane?

Register to view the answer to this question

Hard hats are crucial when climbing a tower crane to protect against head injuries caused by falling objects or potential collisions. The construction site environment poses risks, and workers must be proactive in preventing accidents. Hard hats provide an essential layer of protection, safeguarding the head from impact and trauma. Wearing them is a mandatory safety requirement, ensuring compliance with industry regulations and reducing the likelihood of severe injuries or fatalities. In summary, hard hats are necessary to mitigate risks and maintain a safe working environment while climbing a tower crane.

37. Which parts of the crane is the radius (for lifting) measured from?

Register to view the answer to this question

The radius (for lifting) on a tower crane is typically measured from the center of rotation to the tip of the jib. The jib is the horizontal arm that extends from the crane's tower. Be sure to consult the manufacturer's specifications and recommendations for accurate measurements and safe operation.

38. What is the main purpose of the Rated Capacity Indicator (RCI)?

Register to view the answer to this question

The main purpose of the Rated Capacity Indicator (RCI) in a tower crane is to ensure safe operation by providing real-time information about the crane's load capacity. It helps crane operators monitor and control the loads being lifted, ensuring that they do not exceed the crane's rated capacity. The RCI also helps in preventing overload situations, which can lead to accidents and damage to the crane. By providing accurate load information, the RCI helps maintain safety on construction sites.

39. The operator has to use a new model of tower crane that they are unfamiliar with. What do Regulations (i.e. LOLER 98) and other guidance require the operator to have?

Register to view the answer to this question

Regulations, such as LOLER 98 (Lifting Operations and Lifting Equipment Regulations 1998), require the operator of a tower crane to have appropriate training, knowledge, and experience to safely operate the specific model. Additional guidance may specify that operators should receive familiarization training on new equipment. This ensures proper understanding of the crane's controls, functions, and safety features. Operators should also have competence in interpreting the crane's load chart, as well as overall knowledge of relevant health and safety regulations. Ultimately, the operator must be equipped with the necessary skills and information for safe and efficient operation of the new tower crane.

40. If a load is slewed too fast what TWO factors must the operator (and signaller) take into account?

Register to view the answer to this question

When slewing a load too fast, the operator and signaller must consider two important factors: stability and safety. Firstly, the stability of the tower crane can be compromised if the load is slewed too quickly, potentially leading to tipping or structural failure. Secondly, safety risks arise due to the increased likelihood of the load swinging or colliding with other objects. Consequently, the operator and signaller should carefully assess the load's weight, the crane's rated capabilities, and maintain a controlled and controlled slewing speed to uphold stability and safety during crane operations.

41. What does The Health and Safety at Work Act require employers to do with regards specifically to plant?

Register to view the answer to this question

The Health and Safety at Work Act requires employers to ensure that plant, including tower cranes, is safe to use, properly maintained, and used correctly by trained and competent personnel. Employers must assess and manage the risks associated with plant, provide necessary information, instruction, and training to employees, and implement measures to prevent accidents and ill health. They must also appoint competent supervisors, provide suitable personal protective equipment (PPE), and maintain records of plant inspections, incidents, and maintenance. Overall, the Act emphasizes the duty of employers to prioritize the health and safety of workers when using plant, including tower cranes.

42. Why are some tower cranes rail mounted?

Register to view the answer to this question

Some tower cranes are rail mounted because it allows them to be easily moved along a track. This can be useful on larger construction sites where the crane needs to be positioned at different locations. Rail mounting provides stability and versatility, as the crane can travel along the rail and function effectively. It also eliminates the need for dismantling and reassembling the crane at each new spot.

43. Two cranes are working in the same vicinity that encroach the operating radius of each. What actions would the lift plan or method statement normally specify?

Register to view the answer to this question

The lift plan or method statement would typically specify actions to address the issue of two cranes encroaching each other's operating radius. This could include establishing communication protocols between crane operators, coordinating lift schedules to minimize overlap, creating exclusion zones to prevent collisions, and implementing clear traffic management measures. The plan may also involve appointing a lift supervisor to oversee operations and ensure safe coordination between the two cranes. Ultimately, the aim is to mitigate the risk of accidents and maintain a safe working environment.

44. a)  What happens to the lifting capacity of the crane if the hook block is changed from four falls to two falls and b) What happens to the hoisting speed?

Register to view the answer to this question

a) If the hook block is changed from four falls to two falls, the lifting capacity of the crane typically remains the same. However, the load per fall would double.
b) Changing from four falls to two falls doesn't directly affect the hoisting speed. The hoisting speed is primarily determined by the crane's hoist mechanism and its maximum speed rating.

45. What THREE main duties of The Health and Safety at Work Act must employees follow?

Register to view the answer to this question

The three main duties of The Health and Safety at Work Act that employees must follow are to take reasonable care of their own health and safety, cooperate with their employer in ensuring health and safety, and not to interfere with or misuse anything provided for health and safety.

46. Name FOUR different types or levels of disciplinary actions or sanctions that can be applied (by employers and judicial bodies) to operators of plant who do not comply with, or follow legislation and regulations.

Register to view the answer to this question

Four different types or levels of disciplinary actions that can be applied to operators who do not comply with legislation and regulations are:
1. Verbal Warning: A non-formal reprimand given to the operator orally, highlighting the violation and the consequences of non-compliance.
2. Written Warning: A formal written notice issued to the operator, documenting the violation and potential disciplinary action if further non-compliance occurs.
3. Suspension: Temporary removal of the operator's privileges to operate the plant, usually for a specific period, as a response to repeated or severe non-compliance.
4. Termination: Permanent separation of the operator from their employment due to continued or serious non-compliance with legislation and regulations. Judicial bodies may also impose fines or legal penalties depending on the severity of the violation.

47. a) In what environments are luffing units commonly used and b) why?

Register to view the answer to this question

a) Luffing units are commonly used in dense urban environments where space is limited and buildings are tall. They are also used in areas with high wind conditions or restricted lifting paths.
b) Luffing units are used in these environments because they have a smaller footprint compared to other types of tower cranes. Their ability to lift loads vertically and luff the jib allows for more efficient use of limited space and increased agility in maneuvering around obstacles. The luffing feature also helps to mitigate the effects of wind, making them safer to operate in high wind conditions.

48. Name THREE ways in which wind speed can affect the lifting operation.

Register to view the answer to this question

Wind speed can affect a lifting operation in three ways:
1. Increased wind speed can cause the load to swing, making it difficult to control and potentially hazardous.
2. Strong winds can create additional loads on the crane structure, increasing the risk of instability and structural failure.
3. High wind speeds can make it challenging for the crane operator to accurately position the load, diminishing their control and increasing the chances of accidents.

49. When a crane is sent out on hire what condition must the crane be in?

Register to view the answer to this question

When a crane is sent out on hire, it must be in a safe and operational condition. It must comply with the relevant health and safety regulations and be thoroughly inspected to ensure it's fit for use. Any defects, damages, or issues should be addressed and resolved beforehand. Additionally, the crane should be accompanied by the necessary documentation, such as an up-to-date test certificate and operator manual. It is vital to prioritize safety and maintenance to prevent accidents and ensure the smooth functioning of the crane during the hire period.

50. What is the meaning of this hand signal (being demonstrated by the Tester)?

Register to view the answer to this question

The hand signal being demonstrated by the Tester is for moving the tower crane up vertically. It indicates to the crane operator to lift the load straight up. This signal should be given clearly and decisively to ensure safe and accurate crane operation.

51. What do the words SWL, as stamped on lifting accessories, signify?

Register to view the answer to this question

SWL stands for Safe Working Load. It refers to the maximum weight that a lifting accessory, such as a crane or lifting sling, can safely lift or support during operation. The SWL is determined by engineering calculations and is marked on the accessory to ensure that it is not overloaded, which could lead to accidents or damage. It is crucial to adhere to the SWL and never exceed it, as doing so can compromise safety and be a violation of health and safety regulations.

52. If the hook block inadvertently (accidentally) lands, what course of action should be taken?

Register to view the answer to this question

If the hook block of a tower crane accidentally lands, immediate action must be taken to ensure safety. The first step is to secure the area around the crane and restrict access to dangerous zones. The crane should be inspected for any damage and the operating manual should be consulted for specific instructions. Any necessary repairs should be conducted by a competent person. In serious cases, qualified professionals or the crane's manufacturer may need to be contacted for further guidance. Regular maintenance and inspections are crucial to prevent such incidents in the future.

53. When slewing with a load, where should the operator be looking?

Register to view the answer to this question

When slewing a tower crane with a load, the operator should primarily focus on the load and its position to ensure safe and accurate placement. They should also monitor the crane's movement, making sure it remains stable and aligned with the desired location. Additionally, the operator should be aware of any potential hazards or obstacles in the crane's path. Regular communication with the signal person and maintaining situational awareness is crucial. Overall, the operator's main focus should be on the load and ensuring safe and precise operation.

54. What is the definition of, or how can a hazard be described?

Register to view the answer to this question

A hazard in the context of construction refers to anything that poses a potential danger or risk to health and safety. It can be described as a source, situation, or activity that has the potential to cause harm, injury, or damage. Hazards can encompass various factors such as physical conditions, substances, equipment, processes, and human behavior. Identifying and assessing hazards in a construction site is a crucial step in implementing effective risk management strategies to prevent accidents and ensure the safety of workers and the public.

55. Why should tools and spare components not be left lying on the decks or landings?

Register to view the answer to this question

Tools and spare components should not be left lying on the decks or landings of a tower crane for several reasons. Firstly, it can create a safety hazard as these items can easily fall and potentially injure people working below. Secondly, it can obstruct walkways and impede the movement of personnel, which can lead to accidents. Additionally, leaving tools and spare components on the decks or landings can contribute to a disorganized and cluttered work environment, making it difficult for workers to carry out their tasks efficiently. It is important to maintain a clean and safe working area for everyone involved.

56. Why would a load require netting?

Register to view the answer to this question

A load may require netting to ensure that materials, tools, or debris do not fall from height and cause harm to workers or the public. Netting acts as a protective barrier, preventing objects from being dropped or blown off elevated platforms. It helps to contain loose items and provides a safety measure to minimize the risk of accidents and injury in construction sites. Using netting is a common practice to prevent falling objects and maintain a safe working environment.

57. Why are crane operators generally regarded as 'safety-critical' workers?

Register to view the answer to this question

Crane operators are considered 'safety-critical' as their role directly impacts the safety of construction sites. They control heavy machinery that can cause significant damage and pose risks to workers and the public if not operated properly. Operators must have expert knowledge of safety procedures, load capacities, and site conditions. They must also consider factors like weather, site obstructions, and equipment maintenance. Their vigilance is crucial in preventing accidents and ensuring the safe movement of materials. Due to these responsibilities and potential risks, crane operators are regarded as 'safety-critical' workers in the construction industry.

58. Why should luffing jibs be placed in the correct out-of-service position at the end of the working day?

Register to view the answer to this question

Luffing jibs of tower cranes should be placed in the correct out-of-service position at the end of the day for safety reasons. This prevents the crane from being susceptible to high winds, which can cause the jib to swing uncontrollably. Stowing the luffing jib also reduces the risk of damage to the crane or surrounding structures. It's an important precautionary measure to maintain the integrity of the crane and ensure the safety of workers and the public.

59. During a rest break, or leaving the crane for a short period, what action should be taken for the control box?

Register to view the answer to this question

During a rest break or short period away from the crane, it is important to secure the control box. This can be done by turning off the power supply or using the key switch to activate the lock-out feature. Additionally, the control box should be placed in a safe and locked position, preferably in a dedicated storage area or container. This helps prevent unauthorized access and potential accidents from occurring. Safety precautions should always be followed when dealing with the control box of a tower crane.

60. a) When is a trial lift carried out and b) name THREE checks to be made?

Register to view the answer to this question

a) A trial lift is carried out during the initial setup of the tower crane, before it is put into full operation.
b) Three checks that are typically made before a trial lift include:
1. Ensuring the crane's load chart is properly displayed and accurate.
2. Verifying that all safety devices and indicators are functioning correctly.
3. Conducting a thorough inspection of the lifting gear, including hooks, slings, and shackles, to ensure they are in good condition and suitable for the intended lift.

61. The safe working load or working load limit (SWL/WLL) of a multi-leg chain sling only applies in what TWO conditions or configuration?

Register to view the answer to this question

The safe working load or working load limit (SWL/WLL) of a multi-leg chain sling only applies in two conditions or configurations: first, when the legs are of equal length and are loaded equally, and second, when the angle between the legs is between 45 and 60 degrees. In all other conditions or configurations, the SWL/WLL may not be accurate or applicable. It is important to follow the manufacturer's guidelines and use the correct configuration to ensure safe lifting operations.

62. If a load of 8 tonnes is lifted on two falls or lines of rope, what is the tension in each fall or line?

Register to view the answer to this question

The tension in each fall or line would be approximately 8 tonnes, assuming an even distribution of weight.

63. The number of falls has been changed on the hook block. How has this action affected the RCI?

Register to view the answer to this question

Changing the number of falls on the hook block of a tower crane would have an impact on the Rated Capacity Indicator (RCI). The RCI provides a safety mechanism to prevent overloading the crane. By altering the number of falls, the RCI must be recalibrated to accurately reflect the new load capacity. The crane operator should consult the manufacturer's specifications and guidelines to ensure the RCI is properly adjusted. It may be necessary to seek assistance from a qualified engineer or technician to recalibrate the RCI and ensure safe crane operations.

64. If you are using radios for communication name FIVE checks you must complete before you start lifting?

Register to view the answer to this question

Before starting any lifting operations using radios for communication, five checks that must be completed include checking the integrity of the radio equipment, ensuring clear and effective communication channels, confirming proper functioning of all relevant controls, assessing the stability and capacity of the lifting equipment, and verifying that all personnel involved are trained and aware of their roles and responsibilities. These checks are essential for safe and efficient lifting operations and to minimize potential risks or hazards that may arise during the lifting process.

65. What makes up the total (or gross) weight of a load that is to be lifted?

Register to view the answer to this question

The total weight of a load to be lifted by a tower crane includes the weight of the object itself, any additional equipment or attachments, and any materials or personnel that are part of the load. The weight also takes into account any packaging or containers that may be holding the load. It is essential to accurately assess the total weight to ensure the tower crane is capable of safely lifting and moving the load.

66. Apart from the operator, who else may need to use the machine's Operator's Manual?

Register to view the answer to this question

Other individuals who may need to use the tower crane's Operator's Manual include maintenance technicians, safety inspectors, and supervisors overseeing the operation of the crane. The manual provides detailed information on the crane's assembly, operation, and maintenance procedures, as well as safety precautions to be followed. It serves as a reference for anyone working with the crane, ensuring that proper procedures are understood and executed.

67. What are the THREE actions or stages that a crane operator should undertake during pre-use inspections?

Register to view the answer to this question

The three actions or stages that a crane operator should undertake during pre-use inspections are:
1. Visual inspection: Check for any visible damage, such as cracks or bent components.
2. Functional inspection: Test all controls and mechanisms to ensure they are working properly.
3. Documentation inspection: Review the crane's logbook and any relevant documentation to verify that inspections, maintenance, and repairs have been performed as required.

68. During the lifting operation, part of the task cannot be carried out as detailed in the lift plan. a)  What initially must happen to the lifting operation and b)  who authorises any changes?

Register to view the answer to this question

a) If a part of the task cannot be carried out as detailed in the lift plan, the lifting operation must be stopped immediately.
b) Any changes to the lifting operation must be authorized by a competent person, usually a lift supervisor or an appointed person responsible for overseeing the lifting operation. They will assess the situation, ensure that it is safe to proceed with the changes, and then provide authorization.

69. Wind speeds can be variable throughout the working day. What action must be taken to ensure safe working conditions are maintained?

Register to view the answer to this question

To ensure safe working conditions are maintained during variable wind speeds, tower crane operators should follow proper protocols. This includes regularly monitoring wind speeds and consulting a wind speed indicator. If wind speeds exceed safe limits, they should suspend crane operation and secure the crane according to manufacturer guidelines. Additionally, workers should be notified of the conditions and provided with alternative tasks. Adherence to industry standards and safety regulations is crucial to maintaining a safe working environment amidst variable wind speeds.

70. Name TWO ways that wet weather can affect lifting operations.

Register to view the answer to this question

Wet weather can affect lifting operations in two ways. Firstly, it can make the ground slippery, reducing traction and stability for the crane. This can increase the risk of accidents and make it more challenging to control heavy loads. Secondly, rain or water on the lifting surfaces, such as the crane boom or slings, can decrease friction and potentially cause the load to slip. This can compromise the safety of the operation and lead to damage to the load or surrounding structures. It is crucial to take appropriate precautions and consider weather conditions when planning and executing lifting operations in wet weather.

71. What is meant by a floor-climbing tower crane?

Register to view the answer to this question

A floor-climbing tower crane is a type of crane used in construction. It is designed to vertically climb as the building structure rises. The crane's mast is supported by the building itself, allowing it to lift and transport materials to higher levels without needing to be dismantled and reassembled. The crane is able to climb up the building by adding sections of tower sections as the structure is built. This type of crane provides efficient and flexible lifting capabilities during the construction process.

72. While lifting loads on site what main factor needs to be taken into account?

Register to view the answer to this question

The main factor to consider is the crane's load capacity. It is crucial to ensure that the loads being lifted do not exceed the crane's maximum capacity. Overloading can lead to equipment failure, accidents, and potential damage to the structure. It is also important to assess the stability of the crane's foundation and take into account any environmental conditions, such as high winds or uneven terrain. Regular inspections and maintenance of the crane are essential for safe operations.

73. What checks should be made to the transmitter of a remote-controlled tower crane before work?

Register to view the answer to this question

Before commencing work with a remote-controlled tower crane, the transmitter should undergo several checks. Ensure the battery is adequately charged to prevent interruptions during operation. Inspect the controls for any physical damage or malfunction. Verify that the signal strength is sufficient for reliable communication with the crane. Test all buttons and switches to confirm they are functioning correctly. Review the emergency stop function and its accessibility for prompt use. Additionally, consult the manufacturer's guidelines for specific checks and maintenance procedures.

74. If a load is slewed rather quickly, what TWO initial effects does it have on the load whilst slewing?

Register to view the answer to this question

When a load is slewed quickly, it has two initial effects on the load. Firstly, there is an increase in lateral forces acting on the load, which can lead to increased stress and potentially cause instability. Secondly, the load's momentum increases, resulting in a greater risk of swinging or uncontrolled movement. It is important to ensure that load slewing is carried out gradually and with caution to avoid these effects and maintain safety on the tower crane.

Leave a Comment

Your email address will not be published. Required fields are marked *